The construction site handover for the Mohács Danube Bridge project, carried out by Duna Aszfalt, took place alright. The next step is to issue the work commencement permit.
In late September, the construction site for the Mohács Danube Bridge was handed over, it is being implemented by the Duna Group's flagship company, Duna Aszfalt Zrt. This 756-meter-long bridge will connect the two river banks between Mohács and Újmohács and it will be Hungary's southernmost Danube bridge, developed as part of a project by the Ministry of Construction and Transport (ÉKM). The project includes not only the bridge construction but also the building of over 28 kilometres of road network, along with 13 additional related reinforced concrete bridges and underpasses for cyclists and frame engineering structures as well.
Permits necessary for the actual construction are expected by mid-October, after which first of all some archaeological, ammunition disposal and site preparation tasks will be completed. The primary construction works are expected to commence early next year.